Read Full Story — Energy
A firm providing engineering, procurement, and construction (EPC) services for solar and wind power plants had begun four major projects simultaneously during a period of rising demand for renewable energy. As growth accelerated, the firm's dependence on imported equipment and timely grid connection permits remained the most fragile point of that same growth.
Currency fluctuation raised the cost of imported inverter and turbine equipment by roughly 40% within six months. During the same period, progress payment invoices totaling 38 million TL for two completed projects could not be issued because the grid operator had not yet granted connection approval. As cash inflow fell far short of expectations, the first option raised in management was downsizing the field teams. The general manager argued that rebuilding the technical team would take months, and that this loss would be far more costly during a period when the market itself was growing.
The crisis was managed along three simultaneous lines:
Before any decision about staff was made, senior management took a proportional cut in their own pay, and this step was announced to all teams the same day. In weekly twenty-minute status meetings, the cash position and the state of connection permits were shared without filtering.
While payment-term extension talks were held with suppliers, a partial-delivery, partial-invoicing model was agreed with clients for progress payments on projects, allowing part of the cash to be released early even while connection approval was still pending.
Field engineers who were relatively idle while awaiting connection approval were redirected to preparing technical feasibility and bid files for three new tenders; the crisis period was turned into a period of preparation for the next growth phase.
When grid connection permits were completed at the end of sixteen months, the firm — unlike competitors who had downsized their technical staff during the same period — had retained its entire engineering team intact. The project files prepared in the midst of the crisis allowed the firm to enter new tenders the moment permits were finalized.
In the energy sector, EPC firms sit at the most fragile intersection of currency risk and regulatory/permitting processes; these two risks often arrive not simultaneously but in succession. Protecting the technical team during a crisis is not merely a humane choice — it preserves a competitive advantage that cannot be recaptured once the market is growing again.